Stockton to BakersfieldThursday, Oct. 29, 2026 · RSS
The 99Valley news · Noticias del Valle

News · Noticias · Stockton

Stockton levee next to Brookside is ready for winter

Quick Read

  • What: The Tenmile Slough levee on the west edge of Stockton's Brookside neighborhood has been rebuilt. Officials marked the finish Friday, Oct. 30.
  • Where: About a mile of levee (roughly 5,900 feet) north of March Lane, the Army Corps of Engineers says.
  • Why now: El Niño raises the odds of a wetter-than-average winter, the California Department of Water Resources (DWR) said.
  • What's left: Paving the road on top. "The levee itself is ready to go for winter," the local flood agency's director told ABC10.
  • Bigger picture: It's the first piece of a 23-mile, $1.95 billion project for north and central Stockton, expected to be done in 2037 at the earliest.

The levee that guards Stockton's Brookside neighborhood from the San Joaquin River side is ready for the rainy season. The California Department of Water Resources, the U.S. Army Corps of Engineers, the Central Valley Flood Protection Board and the San Joaquin Area Flood Control Agency marked the end of the Tenmile Slough levee work on Friday, Oct. 30, DWR and ABC10 reported.

Before the project, DWR said, the Tenmile Slough segment was rated the most critically deficient in the Central Valley levee system.

"It's the last line of defense to the heart of Stockton," Darren Suen, executive director of the San Joaquin Area Flood Control Agency, told ABC10.

What was done

Crews rebuilt about a mile of levee, roughly 5,900 feet, along the western border of Brookside, north of March Lane, according to the Army Corps. The work added an underground cutoff wall to stop water from seeping through or under the levee, reshaped the levee to make it more stable and added rock to protect it from erosion. ABC10 reported the seepage walls go 33 to 55 feet deep.

Only paving the road on top of the levee remains, Suen told ABC10.

Why it matters this winter

DWR said El Niño conditions raise the chance of a wetter-than-average winter for much of California, and the state and its partners are getting flood infrastructure ready.

Tenmile Slough is the first part of the Lower San Joaquin River Project, a $1.95 billion effort paid for by DWR, the Army Corps and the local flood agency, DWR said. It covers 23 miles of levee work and two closure structures around north and central Stockton. When the whole project is done, DWR says, it will give better flood protection to 122,000 residents and $28.7 billion in property. The rest of the work is not expected to be finished until at least 2037, ABC10 and the Army Corps reported.

Get ready anyway

San Joaquin County now uses named evacuation zones. Look up yours at SJReady.org so an alert makes sense fast. Questions about the levee project go to the San Joaquin Area Flood Control Agency at 209-475-7020.

Useful links / Enlaces útiles

En español

El dique de Stockton junto a Brookside está listo para el invierno

Lo Básico

  • Qué: Se reconstruyó el dique de Tenmile Slough, en el borde oeste del vecindario Brookside de Stockton. Las autoridades marcaron el fin de la obra el viernes 30 de octubre.
  • Dónde: Cerca de una milla de dique (unos 5,900 pies) al norte de March Lane, según el Cuerpo de Ingenieros del Ejército.
  • Por qué ahora: El Niño aumenta la probabilidad de un invierno más lluvioso de lo normal, dijo el Departamento de Recursos Hídricos de California (DWR).
  • Qué falta: Pavimentar el camino de arriba. "El dique ya está listo para el invierno", dijo a ABC10 el director de la agencia local de control de inundaciones.
  • En grande: Es la primera parte de un proyecto de 23 millas y $1,950 millones para el norte y centro de Stockton, que terminaría en 2037 como pronto.

El dique que protege al vecindario Brookside de Stockton del lado del río San Joaquín está listo para la temporada de lluvias. El DWR, el Cuerpo de Ingenieros del Ejército de EE. UU., la Junta de Protección contra Inundaciones del Valle Central y la Agencia de Control de Inundaciones del Área de San Joaquín marcaron el fin de la obra el viernes 30 de octubre, informaron el DWR y ABC10.

Antes del proyecto, según el DWR, este tramo era el más críticamente deficiente del sistema de diques del Valle Central.

"Es la última línea de defensa del corazón de Stockton", dijo a ABC10 Darren Suen, director ejecutivo de la agencia local.

Qué se hizo

Se reconstruyó cerca de una milla de dique con un muro subterráneo contra filtraciones, una nueva forma más estable y roca contra la erosión. ABC10 informó que los muros llegan a entre 33 y 55 pies de profundidad. Solo falta pavimentar el camino de arriba.

Por qué importa este invierno

El DWR dijo que El Niño aumenta la probabilidad de un invierno más lluvioso. Tenmile Slough es la primera parte del Proyecto del Bajo Río San Joaquín, de $1,950 millones, que mejorará 23 millas de diques. Al terminar, protegerá mejor a 122,000 residentes y $28,700 millones en propiedades. El resto no estaría listo antes de 2037.

Prepárese de todos modos

El condado de San Joaquín usa zonas de evacuación con nombre. Busque la suya en SJReady.org. Preguntas sobre el proyecto: 209-475-7020.